Checked,then published.
What we collect, how we check it, and how to correct us.
1. What the Tracker is, and is not
The Goberera Tracker is an independent civic-accountability tool run by Goberera Initiative Uganda. It connects published budget, procurement, audit and monitoring information about government projects with our own site visits and with moderated observations from citizens, so that anyone can follow a project from the budget to the finished facility. It is not an official government system, and it does not replace the Auditor General, the Inspectorate of Government or the courts.
We start with a pilot in Sembabule District, on public infrastructure (roads, health facilities, schools, water, energy and agricultural facilities), and expand only when the method works.
2. One record, five layers
| Layer | What we record |
|---|---|
| Identity | Permanent ID (GBR-SMB-0001…), name, sector, type, implementing agency, location and precision |
| Money | Approved budget, revisions, releases, recorded expenditure, contract value and variations, each a separate dated event with its source |
| Procurement and implementation | Tender reference, method, contractor, award date, milestones, extensions, completion |
| Progress and evidence | Dated progress observations (never overwritten), photos, inspection reports and documents with page references |
| Accountability | Audit findings and responses, citizen reports and official responses, corrections and the change history |
The data model follows the international Open Contracting for Infrastructure Data Standard (OC4IDS) used by CoST – the Infrastructure Transparency Initiative, simplified for a district pilot.
3. Evidence labels
Every figure and document carries one label, so that what a government body reports is never confused with what has been checked.
Reported by a government body or the implementing agency, with the document and page.
Confirmed by a GIU site visit with dated photos, GPS and a checklist, signed by two monitors.
An observation from the public, published only after moderation. Not an established fact.
Derived by GIU from cited figures using the formulas below.
Contested by a source or an affected party; the right of reply is in progress.
A demonstration record with hypothetical figures, used only to show how the tool works.
4. Measures and formulas
We do not publish an overall “corruption score”. Each measure is shown with its formula and inputs, and is left blank when an input is missing or not comparable.
| Measure | Formula | What it does not tell you |
|---|---|---|
| Budget execution | Recorded expenditure ÷ approved budget × 100 | Whether the money was well spent |
| Release utilisation | Recorded expenditure ÷ funds released × 100 (only when releases are positive and for the same scope and period) | Whether releases were on time |
| Contract cost variation | (Current contract value − original) ÷ original × 100, with approval status and reason | Wrongdoing: many variations are justified |
| Schedule variance | Days between the original and the revised or actual completion date; “behind schedule” only when the baseline is known | Why the delay happened |
| Progress gap | Planned % at the reporting date − reported physical % | Quality of the work |
| Verification gap | Latest official physical % − latest verified physical % | Intent: gaps can come from timing |
| Record completeness | Share of ten essential fields that are filled and sourced | Whether the filled fields are right |
5. Sources and how often we update
- MoFPED Budget Information Portal (budgets, releases, expenditure) – each financial year and quarter.
- PPDA Government Procurement Portal (plans, notices, awards, contracts) – as published.
- Office of the Auditor General (annual, performance and thematic reports) – annually.
- MoFPED Budget Monitoring and Accountability Unit and Office of the Prime Minister monitoring reports.
- Sembabule District Local Government quarterly reports, requested under the Access to Information Act 2005.
- GIU site verification at least twice a year per active project, and after every major milestone.
Each source shows the date we last retrieved it. A project not updated within its reporting cycle is flagged as stale.
6. How we verify
- Desk check: match budget, procurement and progress records using reference numbers; name matches alone are only candidates for review.
- Site visit: two trained monitors, a standard checklist per project type, dated geotagged photos, a conversation with users and the site supervisor.
- Community scorecard: users rate access and quality at a public meeting with district staff present.
- Review: the Social Accountability Officer and the Legal, Compliance & Risk Officer approve before anything is published.
- Right of reply: the responsible office is sent our findings and given 10 working days to respond before publication of any critical finding.
7. Corrections, complaints and right of reply
If you believe a record is wrong, write to tracker@gobererainitiative.org.ug with the project ID and your evidence. We acknowledge within 5 working days and decide within 15. Corrections are shown in the record’s history; nothing is silently deleted. Complaints about our conduct go to the Board Chair through board@gobererainitiative.org.ug.
8. Independence, privacy and the law
Records name the offices and contractors responsible, so the focus stays on the service people were promised. GIU staff with a personal interest in a project do not work on its record. We follow the Access to Information Act 2005, the Data Protection and Privacy Act 2019, the PPDA and PFM Acts and copyright law: we link to source documents rather than republishing them where reuse is unclear, we never publish personal data of citizens who report, and photos of people are used only with consent.